Birdwell Methodist Church

Birdwell Methodist Church                  

Client: 
Consultant QS: 
Start Date:
Finish Date:
Value: 
Birdwell Methodist Church
Auburn Ainsley
June 2003
March 2004
£500,000

 

 

 
Project Description

Construction of steel framed two storey Church with stone brick and block cavity wall envelope and concrete raft.

Full internal fit out including under floor heating.

External works including car-park and small retaining wall.


Challenges

During the excavation works a network of tunnels were discovered.

They were first thought to be the cellars to the former Library.  However, they were found to be the Second World War air-raid shelters for the adjacent school.

Birdwell resident Muriel Trigg attended the school during the war. "The tunnels were not very nice, but the war was a scary time. The tunnels were quite a fair size because the whole school and teachers would go down there".

After extensive discussion on site with the Structural Engineers, sadly the tunnels had to be filled in to maintain the integrity of the new concrete raft foundation.

Design Award

The Scheme was awarded a Special Mention Award at the BMBC Design and Site Stewardship Awards 2003/04.  (See Certificate attached)



Download the project write up in PDF format
pdf icon


Please click on thumbnails to enlarge - When viewing images, please hover over and click the image to view next or previous.

  
 
   Construction Skills Certification Scheme
.....Quality Built In  
Click to view brochure 

 

Inspirational Homes brought to you by Holme Hall Developments, Built by O&P Construction

Be Inspired...

Visit Holme Hall Developments website