Richard Newman primary SchoolRichard Newman Primary School – extension, refurbishment & construction of car park

Client:
Consultant Architect:
Start Date:
Completion Date:
Value:
Barnsley Metropolitan Borough Council
Arcus Consulting
January 2009
September 2009
£730,000

 

 

 

 

Project Description

The main body of work comprised of:

  • Construction of extension to form new Reception Entrance, Offices and toilets.
  • Extension constructed from structural steel frame with cladded roof, concrete raft foundation, aluminium curtain walling, windows and entrance doors.
  • Alteration and refurbishment of areas adjacent to extension.
  • Alteration and refurbishment of the Early Years Centre.
  • Construction of car park including permeable paving.

Challenges

The works had to be carried out without school activities being affected.

This created many difficulties which were overcome with very careful planning and close liaison with the School staff.  The school Easter holiday, half term holidays and summer holidays   and inset days were utilised to the full to minimise disruption to the school.  A small amount of “out of hours” work was carried out to minimise disruption.

The construction of the car park was delayed until the summer holidays and was completed in six weeks and was ready for use     along with the new Entrance Reception when the school staff and pupils returned after the school summer holidays.

Another issue was the surface water off the new car park.  The existing drains were already running to full capacity.  Therefore, to overcome this problem, permeable block paving manufactured by Hanson’s was installed.  This enabled the surface water to soak into the full area of the car park, thus overcoming the problem.

 


Download the project write up in PDF formatpdf icon