Classroom Extension for SEND

at Milton School, Mexborough

Quality Built In

Classroom Extension for SEND at Milton School, Mexborough

The project consisted of the construction of a new single storey extension to form two new classrooms and ancillary rooms.
Including associated external works.

Challenges

The project was on a tight schedule to ensure ready for October Half term. This was to accommodate additional pupils at the school.

The master program was drawn up using Microsoft Project. The critical path operations were highlighted, and operations overlapped where possible to ensure maximum productivity.

The systems of work along with our proactive site manager ensured the project was handed over on time to a very high standard.

Project Details

DATE

October 1, 2020

CLIENT

CYPS Capital Projects

ARCHITECT

Rotherham Metropolitan Borough Council

VALUE

£350k

PROJECT TYPE

Project Gallery